Retention money for subcontractors: how to invoice it and keep your debtors list honest

· NeatSum

On many construction contracts the head contractor keeps back part of each progress payment, often 5%, as security for your work. This is retention money. Some of it is usually released at practical completion, and the rest after the defects liability period, often 12 months later.

Retention causes two bookkeeping problems:

This guide sets out a simple way to handle both problems in NeatSum today. It is general information, not tax or legal advice. Contracts differ, and your accountant or registered BAS or tax agent should confirm the approach for your business.

The short version

  1. Invoice each progress claim for the amount payable now: the claim less the retention.
  2. Keep a list of the retention held for each customer and project, with its release dates.
  3. When retention is due to be released, invoice it as a separate invoice, with GST, due on the date the contract allows.

Done this way, your debtors list only shows money that is actually due. GST lands in the right period on either the cash or the accrual basis.

1. Invoice the progress claim, less retention

Say your third progress claim is $20,000 plus GST, and the contract retains 5%.

Amount
Progress claim 3 $20,000.00
Less 5% retention −$1,000.00
Amount payable now $19,000.00
GST $1,900.00
Invoice total $20,900.00

In NeatSum, create the invoice for $19,000 plus GST. Put the details in the line description so you and your customer can both see them, for example:

Progress claim 3: $20,000.00 less 5% retention $1,000.00 (retention released per contract clause 12)

Use the due date your contract sets for progress payments. If the head contractor pays $20,900, the invoice is paid in full and nothing is left on your debtors list.

2. Keep a list of the retention held

Retention you haven't invoiced yet isn't in your accounts, so keep a simple register of it. A spreadsheet is fine. For each claim, record:

Put the release dates in your calendar. Retention that nobody remembers to claim is retention that often isn't paid.

3. Invoice the retention when it is released

When the contract says the retention (or part of it) can be released, create a new invoice in NeatSum:

Amount
Release of retention, progress claim 3 $1,000.00
GST $100.00
Invoice total $1,100.00

Date it on the day you issue it, and set the due date your contract allows for releasing retention. From then on it ages and gets reminders like any other invoice, which is now correct, because the money really is due.

How the GST works

The ATO's rule for accrual-basis businesses is a legislative instrument: the Goods and Services Tax: (Particular Attribution Rules for Retention Payments) Determination 2017, available on the Federal Register of Legislation. Your registered agent can confirm how it applies to your contracts.

Things to avoid

If you hold retention from your own subcontractors

The same rules apply in reverse. On the accrual basis, the GST credit on retention you hold is claimed when the retention is invoiced or paid, not with the progress claim. The simplest match is to enter each subcontractor bill for the amount payable now, and the retention as its own bill when you release it.

Some states also require head contractors to hold retention in a trust account, for example on most contracts over $20,000 in Western Australia and on large projects in New South Wales and Queensland. Check your state's security of payment rules, or ask your adviser.

Where NeatSum fits

NeatSum is AI-powered Australian cloud accounting software for small and medium businesses. It prepares the BAS from your invoices and bills on a cash or accrual basis, and its aged receivables report, reminders and dashboard all use the invoice's due date. Invoicing retention when it is released, as above, keeps all of them accurate.

For more on the tax itself, read how GST works for Australian businesses and what a BAS is.


← All posts